Contact the team
Office Number (08:00 – 18:00 Monday – Friday): 07887 846640
Out of Hours Emergency Number: CSA Security - 07930 613219
Email: TQA1community@srm.com
Site working
Monday – Friday (08:00 – 18:00)
Saturday (08:00 – 13:00)
Temple Quarter Enterprise Campus (TQEC) is a flagship development that brings the University of Bristol to the commercial centre of the city, to the east of Brunel’s iconic Temple Meads station, to anchor it in the economic renaissance and renewal of Bristol and the wider city-region. TQEC will provide the space to reimagine the University’s role as one of the world’s great civic universities, empowering and enabling a transformed relationship with the city region, its businesses, communities, and government.
The TQA1 (Temple Quarter Academic 1) Building will support the economic growth of Bristol and the wider West of England by:
See rendered images of scheme design for the TQA1 building;
Office Number (08:00 – 18:00 Monday – Friday): 07887 846640
Out of Hours Emergency Number: CSA Security - 07930 613219
Email: TQA1community@srm.com
Monday – Friday (08:00 – 18:00)
Saturday (08:00 – 13:00)
Delivery at TQA1 continues on programme and works are progressing well, with a workforce of up to 400 personnel on site per day, and with over 650,000 person-hours worked on site since commencement.
On the main facade the unitised cladding manufacture is complete, with over 1,200 unitised glazing panels now installed.
Atrium rooflights are currently being fabricated offsite in Gloucester, with the north atrium units installed, with guttering and wall panelling progressing, and south atrium commencing. At roof level, insulation and paving finishes have commenced.
Internally, partition wall installation has commenced to ground, first, second and third floor levels, including plastering and mist coat decoration to Level 01.
Mechanical and electrical installations are progressing on all main floor areas. All prefabricated pipework modules have now been delivered to Levels 01 – 05, with completion of rainwater pipework; completion of dry riser pipework; installation of over 450 fan coil units; and ongoing ductwork and ventilation, soil and vent pipework, sprinkler pipework, electrical containment and installation of panels.
Other works which have taken place within the period have include: installation of monorail track for glass cleaning, sliding partition head tracks, secondary metalwork, precast concrete copings to the external terrace, decorations to internal walls, and completion of internal scaffolding.
BAM Nuttall works to the construction of the Temple Meads Eastern Entrance are nearing completion. The works are due to be protected until it opening in 2026 along with the opening of TQA1.
The project’s Social Return on Investment (SROI) is attributed to local employment, charity work, education talks and work experience programmes. Since commencement of this project, the following have been delivered to contribute to the project SROI:
We endeavour to implement social value on all our projects and leave a positive lasting legacy. For this project we have some ambitious projects and have already funded £24,910 to 11 local charities based in Bristol including:
TQA1 Wider team supported 1625ip Homeless Charity 'Sleep out event' in Bristol raising £1,317.00 for the charity to support their clients.
We are extending our support for homelessness with site initiatives for clothing alongside financial support given to promote opportunities and provide essentials.
We have joined with our client the University of Bristol launching the DEC (Design Engineer Construct) programme in IKB Academy, a local Bristol secondary school, promoting STEM activities in the Built environment.
The accredited learning programme aims to promote and inspire the next generation of professionals into the construction industry by giving them the qualifications they need to succeed. The programme provides students from 13-18+ with the opportunity to increase their knowledge of professional practice in the digital built environment through a programme of study in years 10 and 11, culminating in a DEC GCSE. Beyond this, A or T level options are available to support access into the industry or higher education.
The first session with pupils was on Monday 30th September with the Year 10 and 12 students working on a whole day exercise that saw the evolution of a design for an ‘Eco Classroom’. Members of our team worked with the school staff to deliver the session as did members of the project’s consultant team, Landscape Architect – Grant Associates, and Architect - Feilden Clegg Bradley Studios.
The day finished following presentations which were judged by our staff panel and saw a winner and runners up take away prizes to celebrate their efforts.
Our site is also being used as a learning resource with multiple visits by different engineering groups to support their academic syllabus.
Our social value employment and skills metrics are being tracked as the project progresses and we are now in a position to share the performance against our targets for the project as of the end of January 2024. Further updates will build upon these figures as we look forward towards new trades starting.
Item | KPI | Unit | Achieved | Achieved % | |
1 | Work placements | 50 | People | 25 | 50% |
2 | Jobs created | 35 | People | 32 | 91% |
3 | Construction Careers information, Advice and Guidance events | 27 | Events | 23 | 85% |
4 | Waged training Weeks | 2995 | Weeks | 1207 | 40% |
5 | Qualifying the workforce | 80 | People | 71 | 89% |
6 | Training plans | 9 | Number | 4 | 44% |
7 | Case studies | 4 | Number | 4 | 100% |
Our site was independently assessed by the nationally recognised Considerate Contractors Scheme on January 13th 2025, and was awarded a maximum score of 45 out of 45. This has been made possible by pooling best practice examples from both our business and the wider industry for which we are extremely thankful. Extract of report below.
SCORING | ||
Respect Community | Excellent - 15/15 |
|
Care for the Environment | Excellent - 15/15 |
|
Value their Workforce | Excellent - 15/15 |
|
Total Report Score | Excellent - 45/45 |
Safe access and egress of our site vehicles over the public use of the footpath and cycleways is of paramount importance to us. As such we have worked closely with Bristol City Council over the past 12 months to develop proposals to address the changing needs of the site. In the summer last year we have constructed a new layby and site entrance.
Following initial and footpath and cycleway traffic calming measures, we have extended tarmac roads into the site to aid effective cleaning of transport, and enhanced our site standards by training our full time gate persons to CLOCS Standards.
Our traffic calming measures have been agreed with Bristol City Council, and will be supported using our gate personnel to control our construction traffic. Our aim is united with the council, and our client the University of Bristol, to install effective measures to control the risk to public from the site’s traffic movements.
We have illustrated the approved layout of these measures below;
We aim to ensure our construction activities do not harm the local environment. To drive sustainability on the project we set deliverables around key focus areas. These include both Resource Efficiency and Social Value.
We aim to ensure our construction activities do not harm the local environment. To drive sustainability on the project we set deliverables around key focus areas. These include both Resource Efficiency and Social Value.
The generation of construction waste continues to be a challenge. We utilise ‘take back schemes’ where suppliers collect packaging waste from site, such as wooden pallets. We also have a contract with BWRP (Bristol Wood Recycling Project) to collect and reuse timber from construction. These schemes allow the reuse of materials and reduce our impact on natural resources. Current performance to date includes;
Social Return on Investment - Over £1 Million pounds
Local Employment (South West) - 48%
% Key Building Materials Responsibly Sourced - 99%
Construction Waste Diverted from Landfill - 97%
The 11 GCSE students spent the entire week with us onsite, experiencing the wide range of roles the construction industry offers, whilst gaining real world experience directly onsite. Each day they met and heard from one of our in-house experts from a number of fields, including project management, health and safety, engineering, commercial, and sustainability, followed by onsite demonstrations, from cube crushing, crane operations, steel fixings, bricklaying and concrete operations.
Following this, and taking what they had learnt throughout the week, the students were challenged to build a bridge that would hold the most concrete blocks, a challenge they all rose to, impressing everyone on site.
It was a rewarding week to watch a new generation be inspired, ask questions, and take what they had learnt and put it in to practice, we hope to see them on site soon! A huge thank you to the entire project team from Toureen and to Winterbourne Academy.
Last week the Bristol TQEC (Temple Quarter Enterprise Campus) team delivered the Giant Tetrahedron STEM Challenge workshop to 90 year 7 students at Oasis Temple Quarter Academy over two days.
The day consisted of introducing who NG Bailey are, the different job roles within the engineering industry and how STEM subjects are related to various job roles. Tim Smith Project Director spoke about TQEC project and what the team are currently working on for the university of Bristol with our principal contractor Sir Robert McAlpine.
TQEC is one of the UK’s largest regeneration projects. The campus will be home to 3,000 students and 800 university staff, which will also be a hub for local communities. It is important for us to build relationships with local schools so that they can be part of the build process, and some will eventually move into the campus.
The students were very enthusiastic about building the tetrahedron and showed good teamwork and listening skills. Particular feedback from the students were “ I really liked the giant pyramid that we made, it was the best experience of my life” “It was really fun”.
A big thank you to Richard James head of Oasis Temple Quarter for hosting us, and Sir Robert McAlpine for supporting the team with the workshop.
The Temple Quarter Enterprise Campus (TQEC), part of Bristol’s most ambitious regeneration project, celebrated a major milestone on Thursday, 12 September 2024, with a tr
Read moreWe organised a fantastic 'Dr. Bike road safety event' for our local cycling community, in collaboration with Bristol Council and Better by Bike.
View event pageWe are proud to have built several of its important centres across the UK. Our site recently held a bake sale on 20th May and raised £77.80 + gift aid for the charity.
Our partnership with Maggie's