11th Apr 2023

Westbury Hotel lifted to build basement

Hotel lift takes on a new meaning as we are jacking up the seven-storey Westbury hotel in Mayfair while we excavate under its foundations.

Our Special Projects team have taken on the challenge to create two added layers of basement at The Westbury as part of a project designed to breathe new life into this landmark luxury hotel.

They have been able to draw on the inhouse expertise of colleagues across the business, including members of our McAlpine Lifting Solutions, Geospatial Engineering, and McAlpine Design Group teams, as they look to tackle the various complex engineering challenges presented by the job.

The scheme has involved removing the rear of the concrete frame building and digging down two further levels, extending both out to the site boundary and underneath the existing structure. Once these works are complete, installation of a full height steel frame extension will be significantly increasing the hotel’s square footage. 

But how to hold the building up while we excavate underneath it, remove the old foundations, dig the basement out and install new foundations for the extended structure to sit on?

Step forward McAlpine Design Group, who worked with the project team to develop a solution which involved creating a temporary set of foundations for each existing concrete column.

Under the design, four new piles were drilled 26 metres into the ground through each of the existing foundations and a new steel frame constructed on top to temporarily take the weight of the building off each column.

The weight of the seven storey building was then carefully transferred onto these new temporary foundations using hydraulic jacks.

With the building supported, the team could then start to remove the old foundations and excavate the two new basement floors.

Once the basement is complete, new, permanent steel columns will be installed to extend the existing columns down to the pile caps at the lowest point of the basement.

The weight of the building will then be transferred over to its new foundations and the temporary works removed.

 

Our expertise

  1. McAlpine Design Group

    Thanks to the expertise of our in-house design specialists, we do more than turn our clients’ visions into reality.

    Read more about
  2. Lifting Solutions

    Our in-house McAlpine Lifting Solutions team can help you with complete lifting, access and logistics solutions.

    Read more about
  3. Expertise & Services Geospatial Engineering

    Providing a 360° analysis of land and developments, with minimal disruption onsite.

    Read more about

Latest news

  1. 2 Finsbury Avenue celebrates bottoming out ceremony

    10 Dec 2024

    Guests gathered at the lowest point of the structure’s foundations, just over 50m below ground.

    Read more about
  2. ONE Station Hill reaches practical completion

    06 Dec 2024

    Congratulations to all those who have worked on ONE Station Hill in Reading as the project completes.

    Read more about
  3. Green Apple award for project with sustainability at its core

    27 Nov 2024

    The sustainable approach to delivery taken by our AmeySRM JV team on the A533 Expressway Replacement Bridge Scheme has seen the project honoured with an international Green Apple Environment Award.

    Read more about
View all news