2nd Feb 2023

HS2 celebrates as Chiltern tunnels reach halfway point

Two giant tunnelling machines have passed the halfway mark during the excavation of the 10 mile long Chiltern tunnels, delivered by our Align JV for HS2.

HS2 Ltd confirmed that ‘Florence’ and ‘Cecilia’, the two giant tunnelling machines excavating the high speed rail project’s longest tunnels, have passed the halfway point on their 10 mile journey under the Chilterns.

The enormous 2,000 tonne machines have spent the last 18 months excavating the twin tunnels between the M25 and South Heath in Buckinghamshire that will help protect the environment while improving connections between London, Birmingham and the North.

As well as digging and lining the tunnels, engineers have also completed the excavation of five shafts that will provide ventilation and emergency access near Chalfont St Peter, Chalfont St Giles, Amersham, Little Missenden and Chesham Road. They also recently completed the first breakthrough from a cross passageway to the shaft at Chalfont St Peter.

More than 1.3 million cubic metres of chalk and flint – enough to fill more than 500 Olympic swimming pools - has been excavated and will be used as part of an ambitious chalk grassland restoration project at the south portal of the tunnel. This will see the creation of 127 hectares of new landscaping, wildlife habitat and biodiverse chalk grassland.

Once complete, the Chiltern tunnels will carry high speed trains between London and the North at speeds of up to 200mph (320km/h), helping to improve connections, free up space for more freight and local trains on the existing railway and provide zero carbon journeys for people across the UK.

80 Metres below ground with the engineers building HS2's longest tunnel

Hi, I'm Karine.
And, I'm Ben.
We're both tunnel engineers
on HS2’s Chiltern Tunnels.
We're here today to celebrate
a huge milestone, as each TBM
have reached the halfway point of the 10-mile drive.
We're going to get into one of these buggies here
and take you into the tunnel to show you the progress that we've made.
The 10-mile Chiltern Tunnel is the longest tunnel on the HS2 route.
We're using two tunnelling machines, Florence and Cecilia, to build the tunnel.
So, we're now about 300 metres from the TBM.
We can't drive any further,
so we're going to walk from here to the TBM and
show you around down there.
So we've just arrived at the back of Cecilia
we're on gantry 6 here, about 8km into the tunnel.
As you can see around us
it's quite a busy, noisy environment down here.
We've got the service pipes here, and the tunnel lining.
So this is just one of the 28,000 segments we’ve installed in the tunnel.
These are service pipes in the tunnel.
So we've got Bentonite comes down, which we put into our grout mix.
We've got two dirty water pipes,
for getting all of the water off the machine.
We've got two cooling water pipes at the bottom
which feed cooling water in and out to the TBM to keep
all the drive motors and hydraulics cool. On the other side of the tunnel,
here we've got the two slurry pipes, we've got the feed, the return,
and we also have recycled water on top of that which we can add into the slurry mix
to reduce the density to make it easier for us to pump out the tunnel.
We are at the front of the machine, in front of Cecilia.
The team has just installed another ring in the tunnel.
This segment is one of the 28,000 segments
that we installed so far.
So one ring is made of seven segments. Those segments are precast at the precast factory
outside of the tunnel
and they are supplied via MSV (Multi Service Vehicle)
to the tunnel, to the TBM.
When they arrive at the TBM
they are loaded on to the segment feeder
on to this area, which is the erector area where we are building the rings.
These segments are 2 metres long.
So one excavation is 2 metres.
We’ve installed on each tunnel, 28,000 segment and 4,000 rings,
which corresponds to 8 kilometres for each tunnel.
The TBMs are running well.
We are installing on average around 8 or 9 rings per shift,
so we are on an average of around 32 to 34 metres per day.
So at the moment we're advancing forwards.
We're doing about 60 millimetres a minute, which
trust me is quick for a TBM.
In about 35 minutes,
we'll have advanced 2 metres and we'll have made room to build the next ring.
So we'll build the ring and then we'll repeat the process all over again.
So for both machines, we've excavated just over a million
cubic metres of material to reach the halfway point of the tunnels.
All of that material is being excavated in the cutter head,
pumped out to surface and treated in the slurry treatment plant.
We're about to install another 2 metre concrete ring here,
so we're going to leave the team to it and head out to surface
and see where all of these concrete segments are made,
at the precast factory.
We're now back at surface at the precast factory in the precast yard.
To the left of me here,
you can see the stack of segments that are loaded onto the MSVs,
multi-service vehicles, with the gantry crane over there.
They're sent into the tunnel and then used to build the lining of the tunnel
as the machine progresses.
In total, we need 112,000 segments
to build the 10-mile tunnel.
So far we've installed about 56,000 and we've got a good stock here
and they're still producing them to get us to the end of the tunnel.
So in the background you can see the
back of the STP (slurry treatment plant).
All of the material excavated by both TBMs is treated
and processed by the STP
and then we use all of it for landscaping, so there is no waste.
So here we are back at surface, the tour’s come to an end.
I hope you've enjoyed the update
that we've given you on the progress of our tunnels.
We're looking forward to giving you more updates
in the future as the work progresses.

Martyn Noak, HS2 Ltd’s Head of Tunnel Engineering, said: “It’s great to be able to celebrate the half-way point of this 10-mile long tunnel.  The whole team has put in a fantastic effort over the last year-and-a-half and I’d like to congratulate the crews of both Florence and Cecilia for passing this important tunnelling milestone and thank them for all their hard work.

“This tunnel will take HS2 underneath the Chiltern hills, safeguarding the woodlands and wildlife habits above ground as well as significantly reducing disruption to communities during construction and operation.  Once complete, HS2 will offer low carbon journey options linking London with the major cities of the north and releasing capacity for more freight and local trains on our existing mainlines.”

HS2’s main works contractor, Align – a joint venture formed of three international infrastructure companies: Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick is responsible for the Chiltern tunnel and nearby Colne Valley Viaduct.

Didier Jacques, Align's Underground Construction Director, said: Florence and Cecilia passing the half-way point on what is a long drive for the TBMs, is a great achievement. I would like to pay credit to TGT, our supply chain partner, whose personnel are manning the TBMs.

"This significant progress would not have been possible without the supporting teams on the surface at the South Portal, who supply the thousands of 8.5 tonne segments required to line the tunnels, process the spoil pumped back as slurry through our slurry treatment plant and landscape the chalk produced across the site. Overall, a great team effort." 

Designed specifically for the mix of chalk and flints under the Chilterns, the two identical TBMs are excavating separate tunnels for north and southbound trains. The excavated material is mixed with water to form a slurry, before being pumped back to the surface.

Each machine operates as a self-contained underground factory - digging the tunnel, lining it with concrete wall segments and grouting them into place at a speed of around 15 meters a day. More than 56,000 precision-engineered, fibre-reinforced segments have been installed to create the walls of the tunnels – with each one made on site in a dedicated temporary pre-cast factory.

A crew of 17 people operate each TBM, working in shifts to keep the machines running 24/7. They are supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

As well as the Chiltern tunnels, HS2 also recently launched two TBMs to begin the project’s London tunnels and celebrated the first breakthrough with the completion of the first of two tunnels under Long Itchington Wood in Warwickshire

Latest Infrastructure news

  1. Green Apple award for project with sustainability at its core

    27 Nov 2024

    The sustainable approach to delivery taken by our AmeySRM JV team on the A533 Expressway Replacement Bridge Scheme has seen the project honoured with an international Green Apple Environment Award.

    Read more about
  2. HS2 Colne Valley Viaduct wins design award

    26 Nov 2024

    Colne Valley Viaduct named winner in the 'engineering' category  of the Royal Fine Art Commission Trust’s Building Beauty Awards - 2024 

    Read more about
  3. A19 named England’s No1 road

    08 Nov 2024

    The Strategic Roads User Survey by Transport Focus highlights the remarkable success of the A19 DBFO Project.

    Read more about

Latest news

  1. Raptor cranes at 2 Finsbury Avenue

    10 Jan 2025

    Raptor cranes enhance productivity at 2 Finsbury Avenue, British Land’s iconic dual-tower project redefining Broadgate’s skyline.

    Read more about
  2. 2 Finsbury Avenue celebrates bottoming out ceremony

    10 Dec 2024

    Guests gathered at the lowest point of the structure’s foundations, just over 50m below ground.

    Read more about
  3. ONE Station Hill reaches practical completion

    06 Dec 2024

    Congratulations to all those who have worked on ONE Station Hill in Reading as the project completes.

    Read more about
View all news