3rd Aug 2020

Chiltern tunnels launchpad completed

Our Align JV celebrate a major milestone for the arrival of HS2’s first giant tunnel boring machines (TBMs) with the completion of the 17m high launchpad.

Preparation for the arrival of HS2’s first giant tunnelling machines has passed a major milestone with the completion of the 17m high headwall and ground reinforcement at what will become the south portal of the 10-mile long Chilterns tunnel.

A specialist team, led by our Align JV has spent seven months excavating more than 160,000m3 of material in order to create a level surface from which the two enormous machines will launch early next year.

Weighing in at 2,000 tonnes and stretching for 170m – the two tunnel boring machines (TBMs) are being built by world-leading German tunnelling specialists Herrenknecht and are due to arrive at the site, near to the M25, later in the year.

Alongside the excavation, a specialist team of subcontractors including Roadbridge and KV JV - formed from Keller Group plc and VSL International – have constructed a 17m high headwall through which the TBMs will break to begin their three-year long tunnel drive.

In order to reinforce the ground behind the headwall, more than 636 ‘soil nails’ – some up to 20m long – were driven into the wall and connected to the concrete lining. Each of the nails, consisting of steel or glass fibre reinforced polymer tendons, were inserted using a specialised drilling rig in a delicate operation which can take up two hours.

This reinforcement is required to hold the ground and the surface of the wall in place as the TBMs begin to break through.

Welcoming the milestone, Mark Clapp, HS2 Ltd’s C1 Senior Project Manager said: “Safety is of course our top priority. The new covid-19 processes and procedures put in place by Align ensured that we were able to keep to schedule while keeping everyone safe – and I’d like to thank the whole team for pulling together during what has been a difficult few months for the whole construction industry."

Align Project Director Daniel Altier added: “The completion of the soil nailing is a very visual example of how we are preparing our South Portal site for the arrival of the TBMs later this year. It is now clear for all to see where the TBMs will start their journey. 

"This has been a great team effort by all concerned, considering the challenges caused by Covid-19, including HS2, Align and our colleagues at Roadbridge and the KV JV.” 

Align is delivering the C1 portion of HS2 phase 1 which includes the 10 mile long (16km) twin bore Chilterns tunnel and the 3.4km Colne Valley Viaduct. 

Work on site was paused for four days at the start of the coronavirus lockdown in order to deep clean the work site and put in place new hygiene and social distancing procedures in line with government advice and industry best practice.

Once work is complete, the whole construction site will be landscaped with material excavated from the tunnels, and trees planted in order to blend it in with the surrounding countryside.

To find out more, please visit the Align JV website

Find out more about HS2

  1. HS2 Colne Valley Viaduct wins design award

    26 Nov 2024

    Colne Valley Viaduct named winner in the 'engineering' category  of the Royal Fine Art Commission Trust’s Building Beauty Awards - 2024 

    Read more about
  2. Last segment of Colne Valley Viaduct installed

    06 Sept 2024

    The Colne Valley Viaduct becomes Britain's longest rail bridge after Align JV reaches this major milestone for HS2.

    Read more about
  3. Sector profile: Mike Hickson, Managing Director of Defence

    01 Jul 2024

    Mike Hickson, Sir Robert McAlpine’s newly appointed Managing Director of Defence, shares his vision for the sector and his ambitions for the year ahead.

    Read more about

Latest news

  1. Maggie's Northampton topping out

    21 Feb 2025

    Sir Robert McAlpine Special Projects celebrates the topping out of Maggie’s Northampton, a new cancer support centre at Northampton General Hospital, marking a key milestone in providing expert care for those affected by cancer.

    Read more about
  2. Caroline Mulholland on good design in Healthcare

    12 Feb 2025

    As IHP is Lead Partner of the EHD Champions Awards, Caroline Mulholland reflects on the significance of design in healthcare, international best practice and lessons from the Awards.

    Read more about
  3. National Apprenticeship Week 2025 with Jack Chapman

    11 Feb 2025

    In support of National Apprenticeship week, we caught up with Trainee Quantity Surveyor Jack Chapman to hear about his experiences and progress on the path to a rewarding career.

    Read more about
View all news